Client: EMP (PT Energi Mega Persada Tbk)
Period: 2024 – 2026
Location: Riau, Indonesia
Status: On Going
Project Overview
The Export Line Melibur is an 8-inch underground and above-ground production pipeline, approximately 2.5 km long, running from MSJ-09 well to Simpang Kambing. The Incoming Line Melibur consists of 10-inch, 8-inch, 6-inch and 4-inch pipelines, approximately 5 km long, connecting MSJ-09 well to Melibur Plant.
The project involves replacing the existing pipelines with new ones installed parallel to the old route. The new Export Line will be connected to the existing pipeline at MSJ-09 and Simpang Kambing using the hot tapping method. Before this, the secondary hot tapping on the existing pipeline must be removed.